Following a dilapidation survey by Evesham Mechanical Services Ltd it was concluded that the existing ASHP’s were to be replaced with condensing boilers and associated equipment.
Mikrofill supplied 2 No ETHOS 70kW stainless steel wall mounted boilers c/w integral shunt pumps. The boilers, with a collective turndown ratio of 20 > 1 serve an existing zoned radiator system as well as a primary supply to HWS cylinders. The installation was unvented by way of a new pressurisation package that included a Mikrofill 3 filling device/fluid risk category 4 backflow preventer, a 200 litre expansion vessel and a service drain valve.
The system design and installation was carried out by long standing local contractor Evesham Mechanical Services Ltd.